Cal State University, Dominguez Hills Solar Project

CSU Dominguez Hills
Location: California State University, Dominguez Hills

Project Description: 3,288 solar photovoltaic panels configured in 8 arrays, with the capacity to generate 560 kWdc of peak power and 694,820 kilowatt hours of energy per year, are being installed by SunEdison LLC, with the cooperation and approval of California State University.

The solar photovoltaic system encompasses approximately 3.4 acres on Parking Lot 1 of the CSU campus located in Dominguez Hills, Los Angeles County.

The electricity generated from this project will be delivered directly to the campus under a power purchase agreement with SunEdison LLC, who will own and maintain the system. Construction was completed and the system went online July 2006