| Tasks |
Primary Responsibilities |
| If you are only meeting EA Prerequisite 1 |
If you are meeting both EAp1 and EA credit 3 |
| Designate Commissioning Authority (CxA) |
Owner or Project Team |
Owner or Project Team |
| Document Owner's Project Requirements (OPR) |
Owner |
Owner |
| Develop Basis of Design (BOD) |
Design Team |
Design Team |
| Incorporate commissioning requirements into the construction documents |
Project Team or CxA |
Project Team or CxA |
| Conduct commissioning design review prior to mid- construction documents |
NA |
CxA |
| Develop and implement a commissioning plan |
Project Team or CxA |
Project Team or CxA |
| Review contractor submittals applicable to systems being commissioned |
NA |
CxA |
| Verify the installation and performance of commissioned systems |
CxA |
CxA |
| Develop a systems manual for the commissioned systems |
NA |
Project Team and CxA |
| Verify that the requirements fort training are completed |
NA |
Project Team and CxA |
| Complete a summary commissioning report |
CxA |
CxA |
| Review building operation within 10 months after substantial completion |
NA |
CxA |
This chart outlines the primary responsible party to perform each of the different LEED commissioning requirements and whether they are shared between EAp1 and EAc3 or unique to one or the other. All individuals on the project team are encouraged to participate in the commissioning activities as part of a larger commissioning team.
Source: U.S. Green Building Council, LEED-NC version 2.2 Reference Guide, page 153 (EA P1)
|