Primary Responsibilities Chart for LEED NC v2.2 - EA Prerequisite 1 and EA Credit

 

Tasks Primary Responsibilities
If you are only meeting EA Prerequisite 1 If you are meeting both EAp1 and EA credit 3
Designate Commissioning Authority (CxA) Owner or Project Team Owner or Project Team
Document Owner's Project Requirements (OPR) Owner Owner
Develop Basis of Design (BOD) Design Team Design Team
Incorporate commissioning requirements into the construction documents Project Team or CxA Project Team or CxA
Conduct commissioning design review prior to mid- construction documents NA CxA
Develop and implement a commissioning plan Project Team or CxA Project Team or CxA
Review contractor submittals applicable to systems being commissioned NA CxA
Verify the installation and performance of commissioned systems CxA CxA
Develop a systems manual for the commissioned systems NA Project Team and CxA
Verify that the requirements fort training are completed NA Project Team and CxA
Complete a summary commissioning report CxA CxA
Review building operation within 10 months after substantial completion NA CxA

This chart outlines the primary responsible party to perform each of the different LEED commissioning requirements and whether they are shared between EAp1 and EAc3 or unique to one or the other. All individuals on the project team are encouraged to participate in the commissioning activities as part of a larger commissioning team.

Source: U.S. Green Building Council, LEED-NC version 2.2 Reference Guide, page 153 (EA P1)